Anamer–Bouchfoud Sports Field

A future welcoming and sustainable sports space for children and young people in the region.

Project updates

Information will be published as it is verified.

Progress89%
Construction workLevelling completed; finishing work remains
NeedsMAD 120,000 to complete the work
BudgetApproximately MAD 1.09M total (estimate)
PartnersNo partners at present
Timeline2–3 months after funding is secured (estimate)

Indicative estimate: the total budget assumes that MAD 120,000 represents the remaining 11%. The final amount and timeline will be confirmed after validation.